Water and wastewater

Boondooma Dam Spillway Improvement

Location
Boondooma, QLD
Client
Fulton Hogan, Sunwater
Status
Complete
dji_0067-2

About the project

The Boondooma Dam Spillway Improvement project sought to improve the flood resilience of the dam structure and maintain serviceability during extreme weather events.

Project scope

Install pavement access to site

Construct Spillway Defence System

Construct concrete lining spillway walls

FRP of structural elements

Outcomes

Construction of all-weather access to support connectivity within the site.

Implementation of formwork designs and construction methodologies complying with Sunwater specifications and aligning with most recent codes of a practice.

Working collaboratively and allocating resource that best suits the client’s demands.